Master Building Schedule (pg. 4)


This house building schedule will get you through the process, step-by-step.

It is offered only as a guideline to help planning in the building of your house.  It is based upon the schedule that I use.

No assurance is offered that this list contains every task you will have to perform to successfully complete your house.

Every house building project is unique, with its own specific tasks.  Building code requirements differ by states, counties, and cities.

 


Brick, Siding, Miscellaneous - week 7-8 (continued)

  • Dig underground electric service trench, if needed
  • Have trench pass inspection
  • Refer to floor markings; verify no plugs, switches, or vents are covered by wallboard
  • Hire trim carpenter
  • Have your lumber sales rep do trim material take-off
  • Do exterior clean up of scrap brick, all trash
  • Rough-grade lot
  • Caulk windows, doors, and flashing after brick or siding complete

  

Trim and Miscellaneous - week 9-10

  • Hire painter
  • Order trim material
  • Install trim
  • Frame for concrete flatwork
  • Arrange for concrete delivery
  • Check flatwork forms for level and squareness
  • Make paint color and paint grade selections
  • If brick steps will be added, dig a footing for support
  • Pour concrete flatwork
  • Clean brick

Paint and Miscellaneous  -  week 11-12

  • Return excess trim material
  • Interior clean out
  • Paint prime coat
  • Have wallboard finisher return for touch up on primed walls
  • Finish paint
  • Install garage door
  • Install gutters

 

(cabinets/miscellaneous and mechanical finals schedule next page)

 

 

 

feed0 Comments

Write comment
 
 
quote
bold
italicize
underline
strike
url
image
quote
quote
smile
wink
laugh
grin
angry
sad
shocked
cool
tongue
kiss
cry
smaller | bigger
 

security image
Write the displayed characters


busy